We haven't been able to post any new photos because our house is now fully locked up! I'm happy but at the same time sad because I can't visit and go snap happy when I feel like it. So no photos for this post, sorry! We couldn't tell if some of the plasterwork had been fixed up or not. Our last visit was about 2 weeks ago, so I would assume they'd be fixed by now.
We will be meeting a guy from Victory Blinds this Friday to go through some issues with the plantation shutters we picked. It seems the window handles (for the theatre and masterbedroom) are in the way of the shutters, so he wants to show us what our options are. Works out great because he has the key to the house! I'll be sure to take my camera!
As of today, Metricon has 35 days left to complete our fortress and meet the 1st of July deadline. It doesn't look it should be a problem, but it's cutting it quite close. Just means there will be no room for errors!
According to MyMetricon, internal and external painting will be completed on the 27th and tiling will be done on the 1st June. This means on Friday we should see painted walls! Oooh can't wait!

Whooo Hooo!
ReplyDeletePainting is great and exciting to be able to go through on Friday, make sure you take lots of pics!!!
Cheers
J
Hi G & A,
ReplyDeleteLocked out is the pits! :-( At least they are moving along.
35 days? How exciting!
Hope you had a fabulous time yesterday checking out your newly painted home and took lots of pics!
K.
Hey guys,
ReplyDeleteHanging out for some more pics. Our photos will live here: http://bronwenz.smugmug.com/Other/777131 Plans went to council on Friday so hopefully start the building process soon.
BAH! Went there on Friday and NO painted walls! Only the ceiling and some of the doors were painted. Even the "Fix this, out of square" plasterwork was not fixed, but instead the note was painted over! GrrrrrrrRRRRrr!!!
ReplyDelete-G&A
Hey Bronwen, thanks for the link! I'll certainly be checking on it from time to time.
ReplyDelete-G&A